Question: What does a negative float mean? A. A schedule delay is affecting another project on the same program. B. The project has high risk. C.

What does a negative float mean?

A. A schedule delay is affecting another project on the same program.

B. The project has high risk.

C. The project started before the planned date.

D. The scheduled completion date is after an imposed deadline.