Question: What is the difference between a project baseline and a project plan? A. Project plans change as needed, baselines change only at milestones. B. Project


What is the difference between a project baseline and a project plan?

A.

Project plans change as needed, baselines change only at milestones.

B.

Project plans and baselines do not change-they are amended.

C.

Project plans change as needed; baselines are snapshots of the project plan.

D.

Baselines are control tools; project plans are execution tools.