Question: Which estimation technique performs the estimation at the activity level and then aggregates up to develop estimates for work packages, control accounts, and summary project
Which estimation technique performs the estimation at the activity level and then aggregates up to develop estimates for work packages, control accounts, and summary project levels?
A. Expert judgment B. Bottom-up estimating C. Analogous estimating D. Parametric estimating