Question: Which three Project Scope Management processes use the project charter as an input? A. Plan Scope Management, Create WBS, and Validate Scope B. Create WBS,
Which three Project Scope Management processes use the project charter as an input?
A. Plan Scope Management, Create WBS, and Validate Scope B. Create WBS, Validate Scope, and Control Scope C. Control Scope, Define Scope, and Collect Requirements D. Plan Scope Management, Collect Requirements, and Define Scope