Question: While performing a project work, Riley, the team player, notices a potential new risk, which could impact the project's critical path. He informally discusses the
While performing a project work, Riley, the team player, notices a potential new risk, which could impact the project's critical path. He informally discusses the same with the project manager, who advises him to do something immediately.
What is the most probable suggestion the project manager gave to Riley?
A. Recommend the project be on hold for a day to avoid the risk. B.
Document the risk in the risk register.
C. Record the same in the issue log.
D. Generate a risk report using quantitative and quantitative analysis of the identified risk to alert the team of the schedule impacts.