Question: You are creating a schedule duration estimate for the activities in the PDR Project. Youre working with your project team and comparing the results of
You are creating a schedule duration estimate for the activities in the PDR Project. You’re working with your project team and comparing the results of a past similar project to predict the schedule for the current project. What estimating approach are you using?
A. Organizational process assets B. Parametric C. Analogous D. PERT
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock