Question: You are in the process of developing the scope for the Save Our Schools project. Your program manager, Rachel Janowicz, has asked you to create

You are in the process of developing the scope for the Save Our Schools project. Your program manager, Rachel Janowicz, has asked you to create a rough version of the scope management plan before you actually figure out the scope.Which of the following is not true about the project scope management plan?

A. It describes how the project scope will be defined.

B. It describes how the project scope will be controlled.

C. It is the output of a process called Plan Scope.

D. It describes how the project scope will be verified.