Question: You are managing a software project with limited development resources. The QA department has discovered a large number of defects in the product, and the
You are managing a software project with limited development resources. The QA department has discovered a large number of defects in the product, and the project sponsor is very concerned about this. You want to get the maximum number of defects repaired with minimal effort and cost. Which quality-control tool are you going to use before you direct the efforts of the project team to fixing specific problems?
A. Control chart B. Cause and effect diagram C. Inspection D. Scatter diagram