Question: You are preparing to enter into the project execution with your project team. As part of your preparation, youll rely on your project management plan
You are preparing to enter into the project execution with your project team. As part of your preparation, you’ll rely on your project management plan and several tools and techniques. Which of the following contains parts of the project plan execution?
A. PMIS, WBS, and EVM B. General management skills, status review meetings, and EVM C. Project management methodology and the PMIS D. General management skills, EVM, status review meetings, and interpersonal skills