Question: You are the project manager for a new technology implementation project. Management has requested that your estimates be as exact as possible. Which one of

You are the project manager for a new technology implementation project. Management has requested that your estimates be as exact as possible. Which one of the following methods of estimating will provide the most accurate estimate?

A.

Top-down estimating B.

Top-down budgeting C.

Bottom-up estimating D.

Parametric modeling