Question: You are the project manager for a new training program at your customer's site. This program will require each of the customer's employees to attend
You are the project manager for a new training program at your customer's site. This program will require each of the customer's employees to attend the half-day class and complete an assessment exam. You will be completing the training at the customer's facility, and will need a trainer for the duration of the training, which is six months. This is an example of which of the following?
A.
Resource requirements B.
Assumption C.
Cost constraint D.
A human resource issue