Question: You are the project manager for the DGF Project. This project is to design and implement a new application that will connect to a database


You are the project manager for the DGF Project. This project is to design and implement a new application that will connect to a database server. Management of your company has requested that you create a method to document technical direction on the project and to document any changes or enhancements to the technical attributes of the project deliverable. Which one of the following would satisfy management's request?

A.

Configuration management B.

Integrated Change Control C.

Scope Control D.

Change Management Plan