Question: You are using different tools and techniques to prioritize the risks in your project. Which of the following tools will you not be using? A.
You are using different tools and techniques to prioritize the risks in your project.
Which of the following tools will you not be using?
A. Probability and impact matrix B. Risk urgency assessment C. Risk audits D. Assessment of the risk data quality