Question: You are working to plan procurements for a project that will develop a prototype cruise ship. The prototype will be tested, perfected, and then used
You are working to plan procurements for a project that will develop a prototype cruise ship. The prototype will be tested, perfected, and then used to create a small fleet. In addition to creating a procurement management plan, you must put together bid documents describing the project needs and the criteria that will be used to select a seller. Which of the following will occur during this project's Plan Procurement Management process? A. Make-or-buy decisions B. Answering sellers' questions about the bid documents C. Advertising D. Proposal evaluation