Question: You have identified risks, assessed them using a probability impact matrix, and ranked them according to their priority. What should you do NEXT? A. Plan

You have identified risks, assessed them using a probability impact matrix, and ranked them according to their priority. What should you do NEXT?

A. Plan risk responses.

B. Approve the project management plan.

C. Prepare the top ten list.

D. Identify secondary risks.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Management For Small Projects Questions!