Question: You have identified risks, assessed them using a probability impact matrix, and ranked them according to their priority. What should you do NEXT? A. Plan
You have identified risks, assessed them using a probability impact matrix, and ranked them according to their priority. What should you do NEXT?
A. Plan risk responses.
B. Approve the project management plan.
C. Prepare the top ten list.
D. Identify secondary risks.