Question: You have planned your project and determined the performance baseline, which has been approved. You are all set to go for execution. The approved baseline

You have planned your project and determined the performance baseline, which has been approved. You are all set to go for execution. The approved baseline should be changed when:

A. You spent more than planned on a number of activities.

B. An activity on the critical path has taken longer than scheduled.

C. Some changes that directly or indirectly change or impact the scope, cost, or schedule have been approved.

D. The project is running ahead of schedule.