Question: Your current project is in trouble per reports from the companys project steering committee, with many of the project issues stemming from a lack of
Your current project is in trouble per reports from the company’s project steering committee, with many of the project issues stemming from a lack of resources. What should you do immediately?
A. Tell the steering committee you have analyzed the work performance data, and the work performance reports are wrong.
B. Start with general and background information about the project’s performance.
C. The problems from lack of resources have been noted in variance and trend analysis reports, which you are bringing to the project steering committee to justify more resources.
D. You now need to re-baseline the project’s schedule because of the resource shortage.