Question: Your project has a resource working in niche technology. The functional manager approaches you to release the resource for working on a businesscritical assignment of

Your project has a resource working in niche technology. The functional manager approaches you to release the resource for working on a businesscritical assignment of another project.

What should you do before having further discussion and negotiation with the functional manager?

A. Review the project calendar.

B. Check for a non-billable resource who can complete the assignment assigned to the resource to be released.

C. Review the RACI to know the current assignment of the resource.

D. Immediately escalate the situation to the higher management.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Management For Small Projects Questions!