Question: Your project is to document all the computer systems in your company. Your project team was required to document the operating systems, the hardware, the

Your project is to document all the computer systems in your company. Your project team was required to document the operating systems, the hardware, the network configuration, and the software on each computer. You have finished the project scope according to plan. For the customer to accept the project, what must happen next?

A. Nothing. The plan is complete, so the project is complete.

B. Scope validation should be conducted.

C. Lessons learned should be finalized.

D. Proof-of-concept should be implemented.