Question: Your team worked hard throughout project planning, thoroughly defining and estimating each activity required to complete the work. The resulting network diagram supported the end
Your team worked hard throughout project planning, thoroughly defining and estimating each activity required to complete the work. The resulting network diagram supported the end date that was approved by the team, management, and the stakeholders. As work has progressed, most milestones have been met. On two occasions, workarounds were needed to deal with the occurrence of unidentified risk events. With continued attention to detail, you have been successful in keeping the project on schedule and within budget. Now, an opportunity is identified that can only be realized if the project is completed two days ahead of schedule. Which of the following is the best thing to do when asked to complete a project two days earlier than planned?
A. Tell senior management that the project's critical path does not allow the project to be finished earlier.
B. Tell your manager.
C. Meet with the team to look at options for crashing or fast tracking the critical path.
D. Work hard and see what the project status is next month.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
