A project is defined by the list of activities in Table 13. a. Draw the AOA network.

Question:

A project is defined by the list of activities in Table 13. 

TABLE 13 Activity A ABCDE D F G H I J K L M Immediate predecessors IITOB C  A B B C D, E F, G K J, H Duration

a. Draw the AOA network. 

b. Draw the AON network. 

c. Find the critical path. 

d. Find the total slack and free slack of each activity. 

e. Suppose that activities A, C, I are subject to uncertainty and that only the following time estimates are available:

Activity a A C I 218 m 4 3 11 b 5 4 15

Calculate the probability that the project will be completed in d days, for d = 10, 12, 14, 16, 18, 20. Plot

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question

Project Management Processes Methodologies And Economics

ISBN: 9780130413314

2nd Edition

Authors: Avraham Shtub, Jonathan F. Bard, Shlomo Globerson

Question Posted: