Question: Develop an Excel spreadsheet model to simulate the following set of activities, all of which are normally distributed: Activity A Economic feasibility study B Environmental
Develop an Excel spreadsheet model to simulate the following set of activities, all of which are normally distributed:

Activity A Economic feasibility study B Environmental impact study C Budget approval D Perform work Duration Mean Standard Predecessors 7 years 13 None 6 years None 3 years 1 A, B 1 year 0.1 C