Question: 12. A project that is using the Perform Integrated Change Control process will have many outputs. A member of your team suggests that the project

12. A project that is using the Perform Integrated Change Control process will have many outputs. A member of your team suggests that the project management plan is an output of this process. What should your answer be?

A. Disagree because project management plan updates are outputs.

B. Disagree because the project management plan is not an output.

C. Agree that the project management plan is an output.

D. Disagree because the project management plan is not used in this process.