Question: Question 1 Select all that apply. What are the outputs of the Perform Integrated Change Control process? Select one or more: a. Approved change requests

Question 1

Select all that apply.

What are the outputs of the Perform Integrated Change Control process?

Select one or more:

a. Approved change requests

b. Project management plan updates (any component)

c. Project documents updates (change log)

d. Company procedures regarding change control

e. Organizational process assets

Question 2

Question text

Select all that apply.

What are some key principles of the Perform Integrated Change Control process?

Select one or more:

a. Methods to identify potential and actual changes to the baseline plan must be established

b. Changes must be addressed and managed promptly

c. The impact of changes must be tracked and documented

Question 3

Select all that apply.

What are the inputs to the Close Project or Phase process?

Select one or more:

a. The project management plan

b. Accepted deliverables and agreements

c. Organizational process assets

d. Expert judgment

e. Transition of the deliverable to the customer

f. The project charter

g. Project and business documents

h. Procurement documentation

d. All changes must be in line with risk management plans

e. A change management team must be established to process all changes

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!