Question: 2. When planning a project, influences that can affect the project, whether favorably or unfavorably, must be considered. Which of the following activities would you
2. When planning a project, influences that can affect the project, whether favorably or unfavorably, must be considered. Which of the following activities would you undertake as a project manager to best understand the project environment?
A. Schedule and all resources B. Cultural and social issues C. Project budget approval process D. Detailed requirements analysis