Question: 29. The project scope statement includes constraints, assumptions, and requirements. All of the following are examples of constraints except for which one? A. A preset
29. The project scope statement includes constraints, assumptions, and requirements. All of the following are examples of constraints except for which one?
A. A preset project budget B. A project that has been completed before C. A project due date as defined by management D. A project that requires a mechanical engineer for the month of January
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts