Question: 37. The project charter is an input into which two Project Stakeholder Management processes? A. Identify Stakeholders and Plan Stakeholder Engagement B. Manage Stakeholder Engagement
37. The project charter is an input into which two Project Stakeholder Management processes?
A. Identify Stakeholders and Plan Stakeholder Engagement B. Manage Stakeholder Engagement and Monitor Stakeholder Engagement C. Identify Stakeholders and Manage Stakeholders D. Plan Stakeholder Engagement and Manage Stakeholder Engagement