Question: 47. You will be producing many outputs during the execution phase, such as deliverables, work performance data, and the issue log. You will also be
47. You will be producing many outputs during the execution phase, such as deliverables, work performance data, and the issue log. You will also be implementing which of the following during the execution phase?
A. Project scope, business case, project charter B. Project management plan, communications plan, work breakdown structure (WBS)
C. Procurement management plan, contract statement of work, contract management plan D. Defect repairs, corrective actions, preventive actions