Question: 50. A project manager is completing a project to build a new condo. He needs to confirm that any field drawings by the architect match
50. A project manager is completing a project to build a new condo. He needs to confirm that any field drawings by the architect match the office drawings that will go into the project archives. Which project management system ensures that changes to the project scope and the product scope are thoroughly considered and documented?
A. The change control system B. The integrated change control process C. The configuration management system D. The communication management system