7. The project you have been asked to develop a charter for is complex and has many inputs that are beyond your direct knowledge. Which of the following tools and techniques would best help you proceed with the project chartering process?
A. Matrix management structure B. Available project templates C. Lessons learned D. Expert judgment of others