Question: 7. You will be using earned value management (EVM) on your current project because it is mandated by the project management office (PMO). This means

7. You will be using earned value management (EVM) on your current project because it is mandated by the project management office

(PMO). This means you will need to use:

A. A PMO member on your team B. A project management information system C. A dedicated EVM specialist within your team D. Project-specific contract officers