Question: 8. As you plan your projects resources, you should emphasize the: A. Quality metrics to be collected to evaluate the product, service, or result B.
8. As you plan your project’s resources, you should emphasize the:
A. Quality metrics to be collected to evaluate the product, service, or result B. Costs for each resource C. Desirability of having a dedicated team for each phase of the project D. Need to allocate and account for all resources