Question: 75. Examine the exhibit. How long will the project take if Activity C in the exhibit increases by four days? A. 22 B. 26 C.
75. Examine the exhibit. How long will the project take if Activity C in the exhibit increases by four days?

A. 22 B. 26 C. 16 D. No change because there is float
A 9 6 B P E 3 D 6 G C 3 F H 2