Question: 9. The planned value on your current project at this point in the schedule is $10,000, and the earned value is $9,600. What is the

9. The planned value on your current project at this point in the schedule is $10,000, and the earned value is $9,600. What is the schedule variance?

A. $400.00 B. 0.96 C. –($400.00)

D. 1.04