Question: A project manager discovers additional procurement requirements that were not included in the project plan. What should they do? a) Add the requirements to the

A project manager discovers additional procurement requirements that were not included in the project plan. What should they do?

a) Add the requirements to the procurement management plan immediately

b) Submit a change request for approval through the Perform Integrated Change Control process

c) Reject the additional requirements to avoid changes

d) Update the project charter