Question: A project manager discovers additional work that was not included in the project scope. What should they do? a) Add the work to the project
A project manager discovers additional work that was not included in the project scope. What should they do?
a) Add the work to the project scope immediately
b) Submit a change request for approval through the Perform Integrated Change Control process
c) Reject the additional work to avoid scope creep
d) Update the project charter