Question: Why is it important to involve stakeholders in the Define Scope process? a) To ensure that the project is completed on time b) To ensure
Why is it important to involve stakeholders in the Define Scope process?
a) To ensure that the project is completed on time
b) To ensure that all stakeholder needs and requirements are captured and documented
c) To reduce project costs
d) To increase project scope