Question: A project manager needs to adjust the procurement management plan due to a change in project scope. What process should they follow? a) Plan Procurement
A project manager needs to adjust the procurement management plan due to a change in project scope. What process should they follow?
a) Plan Procurement Management
b) Control Procurements
c) Conduct Procurements
d) Perform Integrated Change Control