Question: A project manager needs to adjust the resource management plan due to a change in project scope. What process should they follow? a) Plan Resource
A project manager needs to adjust the resource management plan due to a change in project scope. What process should they follow?
a) Plan Resource Management
b) Control Resources
c) Manage Team
d) Perform Integrated Change Control