Question: A project manager needs to adjust the project schedule due to a delay in a critical activity. What process should they follow? a) Develop Schedule
A project manager needs to adjust the project schedule due to a delay in a critical activity. What process should they follow? a)
Develop Schedule
b) Control Schedule
c) Define Activities
d) Sequence Activities