Question: A project manager notices a deviation from the project plan. What should they do first? a) Ignore the deviation and continue working b) Document the
A project manager notices a deviation from the project plan. What should they do first?
a) Ignore the deviation and continue working
b) Document the deviation and continue working
c) Analyze the deviation to determine its impact on the project
d) Inform the project sponsor immediately