Question: Consider a project that is to begin work on a Monday and a project team that will not work any weekends. The critical path of
Consider a project that is to begin work on a Monday and a project team that will not work any weekends. The critical path of the project is 17 days. On what day of the week will the project be completed?
A. Monday B. Tuesday C. Wednesday D. Thursday