Question: Consider the following information for a project: Planned Value (PV): 50,000 euro Earned Value (EV): 40,000 euro Based on the given information, calculate the Schedule
Consider the following information for a project:
◾Planned Value (PV): 50,000 euro
◾Earned Value (EV): 40,000 euro Based on the given information, calculate the Schedule Variance (SV) for the project and interpret the result.
A. 10,000 euro; the project is ahead of schedule B. −10,000 euro; the project is behind schedule C. 50,000 euro; the project is ahead of schedule D. −50,000 euro; the project is behind schedule
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
