Question: Consider the following information for a specific activity: Effort required: 40 person-hours Resource availability: 4 persons Work hours per day: 8 hours Based on the
Consider the following information for a specific activity:
◾Effort required: 40 person-hours
◾Resource availability: 4 persons
◾Work hours per day: 8 hours Based on the given information, calculate the duration (in days) required to complete the activity, assuming the work feasible using all the resources available.
A. 1.2 days B. 3.5 days C. 4.3 days D. 5.0 days