Question: Controlling project risks is an ongoing activity to ensure that the risk status has not changed and to react properly and quickly should it change.
Controlling project risks is an ongoing activity to ensure that the risk status has not changed and to react properly and quickly should it change. Which of the following is NOT a valid reason for risk control?
A. To determine if project assumptions are still valid B. To identify trends within risk identification C. To determine if the contingency reserve is adequate D. To determine if vendor contracts are valid