Question: For Activity A, the optimistic cost estimate is $5,000, the most likely estimate is $15,000, and the pessimistic estimate is $21,000. What is the PERT
For Activity A, the optimistic cost estimate is $5,000, the most likely estimate is $15,000, and the pessimistic estimate is $21,000. What is the PERT estimate and standard deviation?
E = ($5,000 + (4 * $15,000) + $21,000) / 6 = $14,333
???? = (25 – 10) / 6 = $2,667
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
