Question: PLEASE ANSWER FAST AND CORRECLTY QUESTION 1 A CPI or SPI value less than one indicates that the project is a. Under cost or behind
PLEASE ANSWER FAST AND CORRECLTY
QUESTION 1
A CPI or SPI value less than one indicates that the project is
| a. | Under cost or behind schedule. | |
| b. | Over cost or ahead of schedule. | |
| c. | Over cost or behind schedule. | |
| d. | Under cost or ahead of schedule. |
1 points
QUESTION 2
Which one of the following is NOT an element of Statement of Work (SOW)
| a. | Schedule constraints | |
| b. | Performance characteristics | |
| c. | Risk analysis | |
| d. | Technical requirements |
1 points
QUESTION 3
Using a contractor to perform a high risk task is which form of risk response?
| a. | Transfer | |
| b. | Acceptance | |
| c. | Avoidance | |
| d. | Mitigation |
1 points
QUESTION 4
Change control requests:
| a. | Are always initiated externally | |
| b. | Provide the baseline against which changes will be controlled | |
| c. | Are inputs to integrated change control | |
| d. | Must be relayed in writing |
1 points
QUESTION 5
Each box is an activity; the number it contains is the duration of the activity in days. The duration of the critical path is:
| a. | 16 days | |
| b. | 19 days | |
| c. | 14 days | |
| d. | 20 days |
1 points
QUESTION 6
Which one of the following are conditions preferred for top-down estimation:
- Time and cost accuracy
- Strategic decision making
- Contract price is fixed
- High uncertainty
| a. | ii and iv | |
| b. | i and iii | |
| c. | i and ii | |
| d. | ii and iii |
1 points
QUESTION 7
Jim receives the following information on his project: PV = 1000, EV = 1200, AC = 800, BAC = 2000, EAC = 1333. How is the project doing in terms of schedule?
| a. | The same amount of work has been done than planned | |
| b. | Less work has been done than planned | |
| c. | The project has cost less than planned | |
| d. | More work has been done than planned |
1 points
QUESTION 8
The lowest level of the WBS is:
| a. | Control account | |
| b. | Work packages | |
| c. | Code of accounts | |
| d. | Deliverable |
1 points
QUESTION 9
An activity has a optimistic duration estimate of 2 days, a mostly likely estimate of 5 days, and a pessimistic estimate of 8 days. What is the PERT weighted average duration?
| a. | 4 | |
| b. | 5.2 | |
| c. | 5 | |
| d. | 6 |
1 points
QUESTION 10
Which of the following is NOT true about the Close Project or Phase process?
| a. | Stakeholders have least amount of influence at this stage. | |
| b. | The probability of completion is the highest at this stage of the project. | |
| c. | Contract closeout must be performed after the Administrative Closeout. | |
| d. | The risk is the lowest at this stage of the project. |
1 points
QUESTION 11
When a company will reduce the number of projects they have to manage internally to only core projects and send noncritical projects to contractors and consulting firms this is called
| a. | Task sharing. | |
| b. | Outsourcing. | |
| c. | Redistribution of projects. | |
| d. | Project allocation. |
1 points
QUESTION 12
Which one of the following is a key decision factor for developing relevant quality standards on a project:
| a. | design work systems | |
| b. | consult project sponsor | |
| c. | understand stakeholders' requirements | |
| d. | identify cost and schedule constraints |
1 points
QUESTION 13
Using the chart below, what is the cost variance?
| a. | $4000 | |
| b. | $5000 | |
| c. | $3000 | |
| d. | $2000 |
1 points
QUESTION 14
Which of the following is NOT part of a modern quality management concept?
| a. | Quality must be inspected in | |
| b. | Performance standard is zero defects | |
| c. | Quality is a 4 cycle process - plan/do/check/act | |
| d. | 85% of failures occur because of the process, not the worker |
1 points
QUESTION 15
Which of the following is not part of the quality assurance process?
| a. | Operational definitions | |
| b. | Quality policy | |
| c. | Quality improvement | |
| d. | Quality audit |
1 points
QUESTION 16
Which one of the following is NOT a key factor in managing customers' expectations:
| a. | Speak the language of the customer | |
| b. | Don't oversell the project | |
| c. | Avoid sharing project risks information | |
| d. | Share signification problems and risks |
1 points
QUESTION 17
Which of the following is an input to the team development process?
| a. | Staffing pool description | |
| b. | Inputs to performance appraisals | |
| c. | External feedback | |
| d. | General management skills |
1 points
QUESTION 18
Project teams can often identify risks by conducting any of several types of reviews. Which of the following illustrates a valuable type of risk review?
| a. | review the project schedule to determine if certain people are overloaded | |
| b. | review previous projects to verify that each current assumption is correct | |
| c. | review sunk costs to determine project continuance | |
| d. | review the communication plan to determine where poor communications could cause a problem |
1 points
QUESTION 19
A method of shortening the duration of the project is:
| a. | Creating milestones | |
| b. | Leveling | |
| c. | Fast tracking | |
| d. | Lead |
1 points
QUESTION 20
An analysis carried out during and shortly after the project life cycle that attempts to capture positive and negative learning is represented in which of the following?
| a. | Performance evaluation | |
| b. | Scenario analysis | |
| c. | Lessons learned | |
| d. | Variance analyses |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
