Question: In a software development project, the cycle time for completing a task is 4 days, and the lead time for delivering the task from the
In a software development project, the cycle time for completing a task is 4 days, and the lead time for delivering the task from the time it is requested is 6 days. What is the wait time in this case?
A. 2 days B. 4 days C. 6 days D. 10 days