Question: The inter-dependencies between the various activities in a network and their mean time durations are given in Table E10.1. Calculate the earliest and latest event

The inter-dependencies between the various activities in a network and their mean time durations are given in Table E10.1. Calculate the earliest and latest event times of each event using forward and backward pass calculations.

Table E10.1 Inter-dependencies between various activities and their mean time durations Activities

Table E10.1 Inter-dependencies between various activities and their mean time durations Activities Depends upon Mean time durations (days) 2 Q NOPORSTUKIN Y N O, S P, Y Q, U N S T, Y N S, X R 23213422312