Question: Use the example graphic shown below to answer this question. If the duration of activity B was changed to 10 days and the duration of
Use the example graphic shown below to answer this question. If the duration of activity B was changed to 10 days and the duration of activity G was changed to 9 days, which of the following is the critical path?
A. A-B-C-E-H B. A-D-E-H C. A-F-G-H D. A-F-G-E-H
7 B 5 C 10 A D 14 E 2 8 H FL F 7 G 6
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts